City defends P4.1-million Diversion Road overpass facelift amid questions on cost, design

A project perspective shows the new roof, finishes, and lighting designed to give pedestrians a safer and more comfortable experience at the Diversion Road overpass in Iloilo City’s Mandurriao district.
A project perspective shows the new roof, finishes, and lighting designed to give pedestrians a safer and more comfortable experience at the Diversion Road overpass in Iloilo City’s Mandurriao district.

ILOILO City – Facing scrutiny over another multimillion-peso upgrade, the City Engineer’s Office (CEO) has gone on the defensive as construction began on the P4.1-million improvement of the Diversion Road overpass in Mandurriao district.

Project Engineer Jonberlie Ladua insisted the project is distinct and not overpriced.

“Wala ni siya sang kaparehas kay every plano, lain-lain man. Wala man guro na may makit-an nga parehas sang iban,” he said, stressing the redesign includes unique elements not seen in other overpasses.

Ladua also brushed aside criticisms of delay.

“Indi siya delayed. Sakto lang siya sa date kay August 11 ang Notice to Proceed, nagpang-purchase pa na sang materials ang contractor, kag iban pa nga kinahanglanon,” he explained.

The project, awarded to Stonebuilt Construction Services, formally started on September 24, and targets completion on December 8.

The scope covers roof and steel framing upgrades, LED lighting, anti-slip decorative tiles, repainting, plumbing, and additional safety features.

On the issue of pricing, Ladua pointed to detailed estimates made by the CEO.

“May estimate kami nga ginhimo kag husto ang quantity. May allowance man kita nga allowable man kag ang presyo natun may pricelist man kita nga ginabasehan,” he said.

Funding comes from the city’s Development Fund SB #2 FY-2024.

The Diversion Road overpass, built in 2015 at a cost of P20 million, has long been a symbol of underutilization after its two elevators – intended for senior citizens and persons with disabilities – never worked despite a P5.1-million repair allocation last year.

Now, the city government hopes the facelift will erase that legacy and finally deliver a modern, functional, and commuter-friendly crossing./PN