Boracay power system rehab ‘only 20% done’

The Aklan Electric Cooperative is still relocating power posts and distribution lines in Boracay. AKELCO

BORACAY – Rehabilitation works for this island resort’s power system is only 20-percent complete, according to the Aklan Electric Cooperative (Akelco).

The province’s sole power distributor has been relocating power posts and lateral distribution lines as the island resort undergoes its half-year rehabilitation which began on April 26.

Akelco assistant general manager for engineering Joel Martinez said the relocation of the power facilities will shift into high gear this week.

But he stressed that the power system upgrade will go beyond the island’s Oct. 26 scheduled reopening.

Madami ang apektadong poste at linya ng kuryente na ating i-rerelocate dahil sa road widening,” said Martinez. “Kahit mag-open ang Boracay patuloy pa rin tayo sa paglipat ng mga electric posts para malinis natin ang mga cross lines sa kalsada at mailagay sa tamang lokasyon ang mga distribution lines.”

The Department of Public Works and Highways is working on a road widening project in Boracay, covering the stretch from Cagban to Balabag.

The road project – which aims to address the traffic problem in Boracay – has affected private properties, mobile service providers, drainage systems, and telephone lines in the island. (With a report from Aklan Forum Journal/PN)